Program Overview
In this virtual reality module, participants will have access to a simulated excavation site, focused on completing gas pipeline hot tapping tasks in the neighborhood. The module includes abandonment, main extension and cut-out scenarios. Using available materials and resources, the player must determine the order of actions and complete the task.
Core Learning Objectives
-
Safety Measures — take all necessary safety measures
-
Work Sequence — accomplish task according to the technological process
-
AOC Recognition — notifying and dealing with AOCs
-
Reporting/Documentation — steps taken / resolution / documentation
Tools
-
Laser Pointer — to interact with menus and objects in this experience, aim the laser pointer at an interactable item and pull the controller trigger to select it
-
Soap Spray — to test for a leak, aim the spray and pull the controller trigger:
-
If bubbles appear, there is a leak.
-
If there are no bubbles, the leak is coming from somewhere else.
-
-
CGI Tool — to take a reading, aim the tool and pull the controller trigger.
Instructor Mode
Use the "Add Scenario" screen in the lobby to build a specific scenario. You will be able to select:
- Scenario (1-3)
- Turn Hints ON / Turn Hints OFF
- How Many AOCs are present
- Which AOCs are present
How to Get 100%
There are 3 different scenarios that can appear within the module. If you are not using Instructor Mode, these will appear randomly.
Note: In this module, if a user performs the wrong action for the second time, a warning window will appear again and the correct action will be automatically performed.
All Scenarios
-
Read and Close Work Order
-
Report AOCs through Wrist Menu
-
Complete the scenario's unique steps
-
Once the scenario is complete, open Wrist Menu > Communication Menu
-
Select "Report about work completion and leave"
-
-
Select “Report and finish the scenario”
Abandonment Scenario
- Enter Excavation (select ladder with laser pointer, then select Climb Down)
- Install 4" stopper fitting (select main pipe to open menu)
- Pressure Test 4" stopper fitting
- Install 1" Self-tapping tees for gauges and vent stack (3 minimum)
- Pressure Test — 1" Self-tapping tees for gauges and vent stack
- Install pressure gauge on 1" self-tapping tees
- Install vent stack on 1" self tapping tee
- Tap 1" Self-tapping tees for gauges and vent stack (Install, Tap, Cap)
- Confirm pipe pressures on gauges and monitor
- Install gate valve on 4" stopper fitting
- Test Gate valve for proper operation (open/close gate)
- Install D5 drilling machine onto gate valve
- Open Gate valve
- Lower D5 Drilling machine through gate valve onto pipe
- Operate D5 Drilling machine to tap pipe
- Raise D5 Drilling machine after pipe is tapped
- Close Gate valve
- Relieve Pressure from Gate Valve (open the valve)
- Remove D5 drilling machine
- Confirm pipe coupon is present in shell cutter on drilling machine
- Install D5 stopper unit
- Open Gate valve
- Lower D5 stopper unit
- Set Stoppers — D5 Stopper unit
- Open vent stack gate valve to relieve downstream pressure
- Confirm gauge pressures on 1" tapping tees (upstream/downstream)
- Install bonding cables
- Cut Pipe (2 cuts)
- Remove Pipe section
- Install 4" pipe end cap
- Close vent stack valve
- Operate D5 Stopper assembly (Release Stopper)
- Raise D5 Stopper assembly
- Close Gate valve
- Purge the air through the vent stack
- Soap Test — 4" End Cap
- Relieve Pressure from Gate Valve
- Remove stopper assembly
- Install plug inserter onto valve
- Open Gate valve
- Lower D5 plug inserter through valve
- Operate D5 plug inserter — insert/release plug
- Relieve Pressure from Gate Valve
- Raise D5 plug inserter
- Close Gate valve
- Relieve Pressure from Gate Valve
- Remove D5 plug inserter
- Remove Gate valve (4")
- Install 4" Stopper Fitting Cap
- Remove Pressure gauges from 1" self-tapping tees and cap tees
- Remove vent stack from 1" self-tapping tees and cap tee
- Soap Test all fittings
- Work Completed — Contact Supervisor and End Session
Main Extension Scenario
- Enter Excavation (select ladder with laser pointer, then select Climb Down)
- Install 4" stopper fitting (select main pipe to open menu)
- Pressure Test 4" stopper fitting
- Install 1" Self-tapping tees for gauges and vent stack (2 minimum)
- Pressure Test — 1" Self-tapping tees for gauges and vent stack
- Install pressure gauge on 1" self-tapping tees
- Install vent stack on 1" self tapping tee
- Tap 1" self-tapping tees for gauges and vent stack (Install, Tap, Cap)
- Confirm pipe pressures on gauges and monitor
- Install gate valve on 4" stopper fitting
- Test Gate valve for proper operation (open/close gate)
- Install D5 drilling machine onto gate valve
- Open Gate valve
- Lower D5 Drilling machine through gate valve onto pipe
- Operate D5 Drilling machine to tap pipe
- Raise D5 Drilling machine after pipe is tapped
- Close Gate valve
- Relieve Pressure from Gate Valve (open the valve)
- Remove D5 drilling machine
- Confirm pipe coupon is present in shell cutter on drilling machine
- Install D5 stopper unit
- Open Gate valve
- Lower D5 stopper unit
- Set Stoppers — D5 Stopper unit
- Open vent stack gate valve to relieve downstream pressure
- Confirm gauge pressures on 1" tapping tees (upstream/downstream)
- Install bonding cables
- Cut Pipe
- Remove Pipe section
- Pressure Test New Pipe Section
- Install New Pipe Section
- Close vent stack valve
- Operate D5 Stopper assembly (Release Stopper)
- Raise D5 Stopper assembly
- Close Gate valve
- Soap Test — 4" transition fitting weld
- Purge air from new section of pipe
- Relieve Pressure from Gate Valve
- Remove stopper assembly
- Install plug inserter onto valve
- Open Gate valve
- Lower D5 plug inserter through valve
- Operate D5 plug inserter — insert/release plug
- Relieve Pressure from Gate Valve
- Raise D5 plug inserter
- Close Gate valve
- Relieve Pressure from Gate Valve
- Remove D5 plug inserter
- Remove Gate valve (4")
- Install 4" Stopper Fitting Cap
- Remove Pressure gauges from 1" self-tapping tees and cap tees
- Remove vent stack from 1" self-tapping tees and cap tee
- Soap Test all fittings
- Work Completed — Contact Supervisor and End Session
Main Cut-Out Scenario
- Enter Excavation (select ladder with laser pointer, then select Climb Down)
- Install 4" stopper fitting (2 minimum) (select main pipe to open menu)
- Pressure Test 4" stopper fitting
- Install 1" Self-tapping tees for gauges and vent stack (4 minimum)
- Pressure Test — 1" Self-tapping tees for gauges and vent stack
- Install pressure gauge on 1" self-tapping tees
- Install vent stack on 1" self tapping tee
- Tap 1" self-tapping tees for gauges and vent stack (Install, Tap, Cap)
- Confirm pipe pressures on gauges and monitor
- Note: The user has to keep gauge on pipe section #1 in their line of site for 3 seconds
- Install gate valve on 4" stopper fitting
- Test Gate valve for proper operation (open/close gate)
- Install D5 drilling machine onto gate valve
- Open Gate valve
- Lower D5 Drilling machine through gate valve onto pipe
- Operate D5 Drilling machine to tap pipe
- Raise D5 Drilling machine after pipe is tapped
- Close Gate valve
- Relieve Pressure from Gate Valve
- Remove D5 drilling machine
- Confirm pipe coupon is present in shell cutter on drilling machine
- Install D5 stopper unit
- Install Bypass
- Open Gate valves
- Lower D5 stopper unit
- Set Stoppers — D5 Stopper unit
- Open vent stack valve to vent gas pressure between stoppers
- Close vent stack valve
- Confirm gauge pressures on 1" tapping tees (upstream/downstream)
- Install bonding cables
- Cut Pipe (2 cuts)
- Remove Pipe section
- Install pre-tested replacement pipe section
- Operate D5 Stopper assembly (Release Stopper)
- Purge gas through vent stack (Open valve)
- Close vent stack valve
- Operate D5 Stopper assembly (Release Stopper)
- Raise D5 Stopper assembly
- Close Gate valve
- Soap Test — 4" the butt weld on replacement pipe (two)
- Relieve Pressure from Gate valve
- Remove the bypass line
- Remove stopper assembly
- Install plug inserter onto valve
- Open Gate valve
- Lower D5 plug inserter through valve
- Operate D5 plug inserter — insert/release plug
- Relieve Pressure from Gate Valve
- Raise D5 plug inserter
- Close Gate valve
- Relieve Pressure from Gate Valve
- Remove D5 plug inserter
- Remove Gate valve (4")
- Install 4" Stopper Fitting Cap
- Remove Pressure gauges from 1" self-tapping tees and cap tees
- Remove vent stack from 1" self-tapping tees and cap tee
- Soap Test all fittings
- Work Completed — Contact Supervisor and End Session
For a more detailed walkthrough of the module, see the Gas Pipeline Handling User Guide.