Home > Module Guides > Trainer Guides > Gas Pipeline Handling – Trainer Guide
Gas Pipeline Handling – Trainer Guide
print icon


Program Overview

In this virtual reality module, participants will have access to a simulated excavation site, focused on completing gas pipeline hot tapping tasks in the neighborhood. The module includes abandonment, main extension and cut-out scenarios. Using available materials and resources, the player must determine the order of actions and complete the task.

 

Core Learning Objectives

  • Safety Measures — take all necessary safety measures

  • Work Sequence — accomplish task according to the technological process

  • AOC Recognition — notifying and dealing with AOCs

  • Reporting/Documentation — steps taken / resolution / documentation

Tools

  • Laser Pointer — to interact with menus and objects in this experience, aim the laser pointer at an interactable item and pull the controller trigger to select it

  • Soap Spray — to test for a leak, aim the spray and pull the controller trigger:

    • If bubbles appear, there is a leak.

    • If there are no bubbles, the leak is coming from somewhere else.

  • CGI Tool — to take a reading, aim the tool and pull the controller trigger.

 

Instructor Mode

Use the "Add Scenario" screen in the lobby to build a specific scenario. You will be able to select:

  • Scenario (1-3)
  • Turn Hints ON / Turn Hints OFF
  • How Many AOCs are present
  • Which AOCs are present

 

How to Get 100%

There are 3 different scenarios that can appear within the module. If you are not using Instructor Mode, these will appear randomly.

 

Note: In this module, if a user performs the wrong action for the second time, a warning window will appear again and the correct action will be automatically performed.

All Scenarios

  1. Read and Close Work Order

  2. Report AOCs through Wrist Menu

  3. Complete the scenario's unique steps

  4. Once the scenario is complete, open Wrist Menu > Communication Menu

    1. Select "Report about work completion and leave"

  5. Select “Report and finish the scenario

 

Abandonment Scenario

  1. Enter Excavation (select ladder with laser pointer, then select Climb Down)

  1. Install 4" stopper fitting (select main pipe to open menu)
  2. Pressure Test 4" stopper fitting

  1. Install 1" Self-tapping tees for gauges and vent stack (3 minimum)
  2. Pressure Test — 1" Self-tapping tees for gauges and vent stack 
  3. Install pressure gauge on 1" self-tapping tees 
  4. Install vent stack on 1" self tapping tee
  5. Tap 1" Self-tapping tees for gauges and vent stack (Install, Tap, Cap)
  6. Confirm pipe pressures on gauges and monitor
  7. Install gate valve on 4" stopper fitting
  8. Test Gate valve for proper operation (open/close gate)
  9. Install D5 drilling machine onto gate valve 
  10. Open Gate valve 
  11. Lower  D5 Drilling machine through gate valve onto pipe 
  12. Operate D5 Drilling machine to tap pipe
  13. Raise D5 Drilling machine after pipe is tapped
  14. Close Gate valve  
  15. Relieve Pressure from Gate Valve (open the valve)
  16. Remove D5 drilling machine
  17. Confirm pipe coupon is present in shell cutter on drilling machine
  18. Install D5 stopper unit
  19. Open Gate valve 
  20. Lower D5 stopper unit 
  21. Set Stoppers — D5 Stopper unit 
  22. Open vent stack gate valve to relieve downstream pressure
  23. Confirm gauge pressures on 1" tapping tees (upstream/downstream)
  24. Install bonding cables
  25. Cut Pipe (2 cuts)
  26. Remove Pipe section
  27. Install 4" pipe end cap
  28. Close vent stack valve 
  29. Operate D5 Stopper assembly (Release Stopper)
  30. Raise D5 Stopper assembly
  31. Close Gate valve  
  32. Purge the air through the vent stack
  33. Soap Test — 4" End Cap 
  34. Relieve Pressure from Gate Valve 
  35. Remove stopper assembly
  36. Install plug inserter onto valve 
  37. Open Gate valve  
  38. Lower D5 plug inserter through valve
  39. Operate D5 plug inserter — insert/release plug
  40. Relieve Pressure from Gate Valve 
  41. Raise D5 plug inserter 
  42. Close Gate valve  
  43. Relieve Pressure from Gate Valve 
  44. Remove D5 plug inserter 
  45. Remove Gate valve (4")
  46. Install 4" Stopper Fitting Cap
  47. Remove Pressure gauges from 1" self-tapping tees and cap tees
  48. Remove vent stack from 1" self-tapping tees and cap tee
  49. Soap Test all fittings

  1. Work Completed — Contact Supervisor and End Session

 

Main Extension Scenario

  1. Enter Excavation (select ladder with laser pointer, then select Climb Down)
  2. Install 4" stopper fitting (select main pipe to open menu)
  3. Pressure Test 4" stopper fitting
  4. Install 1" Self-tapping tees for gauges and vent stack (2 minimum)
  5. Pressure Test — 1" Self-tapping tees for gauges and vent stack 
  6. Install pressure gauge on 1" self-tapping tees 
  7. Install vent stack on 1" self tapping tee
  8. Tap 1" self-tapping tees for gauges and vent stack  (Install, Tap, Cap)
  9. Confirm pipe pressures on gauges and monitor
  10. Install gate valve on 4" stopper fitting
  11. Test Gate valve for proper operation (open/close gate)
  12. Install D5 drilling machine onto gate valve 
  13. Open Gate valve 
  14. Lower D5 Drilling machine through gate valve onto pipe 
  15. Operate D5 Drilling machine to tap pipe
  16. Raise D5 Drilling machine after pipe is tapped
  17. Close Gate valve  
  18. Relieve Pressure from Gate Valve (open the valve)
  19. Remove D5 drilling machine
  20. Confirm pipe coupon is present in shell cutter on drilling machine
  21. Install D5 stopper unit
  22. Open Gate valve 
  23. Lower D5 stopper unit 
  24. Set Stoppers — D5 Stopper unit 
  25. Open vent stack gate valve to relieve downstream pressure
  26. Confirm gauge pressures on 1" tapping tees (upstream/downstream)
  27. Install bonding cables
  28. Cut Pipe 
  29. Remove Pipe section
  30. Pressure Test New Pipe Section
  31. Install New Pipe Section
  32. Close vent stack valve 
  33. Operate D5 Stopper assembly (Release Stopper)
  34. Raise D5 Stopper assembly
  35. Close Gate valve  
  36. Soap Test — 4" transition fitting weld
  37. Purge air from new section of pipe
  38. Relieve Pressure from Gate Valve 
  39. Remove stopper assembly
  40. Install plug inserter onto valve 
  41. Open Gate valve  
  42. Lower D5 plug inserter through valve
  43. Operate D5 plug inserter — insert/release plug
  44. Relieve Pressure from Gate Valve 
  45. Raise D5 plug inserter 
  46. Close Gate valve  
  47. Relieve Pressure from Gate Valve 
  48. Remove D5 plug inserter 
  49. Remove Gate valve (4")
  50. Install 4" Stopper Fitting Cap
  51. Remove Pressure gauges from 1" self-tapping tees and cap tees
  52. Remove vent stack from 1" self-tapping tees and cap tee
  53. Soap Test all fittings
  54. Work Completed — Contact Supervisor and End Session

Main Cut-Out Scenario

  1. Enter Excavation (select ladder with laser pointer, then select Climb Down)
  2. Install 4" stopper fitting (2 minimum) (select main pipe to open menu)
  3. Pressure Test 4" stopper fitting 
  4. Install 1" Self-tapping tees for gauges and vent stack (4 minimum)
  5. Pressure Test — 1" Self-tapping tees for gauges and vent stack 
  6. Install pressure gauge on 1" self-tapping tees 
  7. Install vent stack on 1" self tapping tee
  8. Tap 1" self-tapping tees for gauges and vent stack (Install, Tap, Cap)
  9. Confirm pipe pressures on gauges and monitor
  10. Note: The user has to keep gauge on pipe section #1 in their line of site for 3 seconds
  11. Install gate valve on 4" stopper fitting
  12. Test Gate valve for proper operation (open/close gate)
  13. Install D5 drilling machine onto gate valve 
  14. Open Gate valve 
  15. Lower D5 Drilling machine through gate valve onto pipe 
  16. Operate D5 Drilling machine to tap pipe
  17. Raise D5 Drilling machine after pipe is tapped
  18. Close Gate valve  
  19. Relieve Pressure from Gate Valve 
  20. Remove D5 drilling machine
  21. Confirm pipe coupon is present in shell cutter on drilling machine
  22. Install D5 stopper unit 
  23. Install Bypass
  24. Open Gate valves
  25. Lower D5 stopper unit 
  26. Set Stoppers — D5 Stopper unit 
  27. Open vent stack valve to vent gas pressure between stoppers
  28. Close vent stack valve 
  29. Confirm gauge pressures on 1" tapping tees (upstream/downstream)
  30. Install bonding cables
  31. Cut Pipe (2 cuts)
  32. Remove Pipe section
  33. Install pre-tested replacement pipe section
  34. Operate D5 Stopper assembly (Release Stopper)
  35. Purge gas through vent stack (Open valve)
  36. Close vent stack valve 
  37. Operate D5 Stopper assembly (Release Stopper)
  38. Raise D5 Stopper assembly
  39. Close Gate valve  
  40. Soap Test — 4" the butt weld on replacement pipe (two)
  41. Relieve Pressure from Gate valve 
  42. Remove the bypass line
  43. Remove stopper assembly
  44. Install plug inserter onto valve 
  45. Open Gate valve  
  46. Lower D5 plug inserter through valve
  47. Operate D5 plug inserter — insert/release plug
  48. Relieve Pressure from Gate Valve 
  49. Raise D5 plug inserter 
  50. Close Gate valve  
  51. Relieve Pressure from Gate Valve 
  52. Remove D5 plug inserter 
  53. Remove Gate valve (4")
  54. Install 4" Stopper Fitting Cap
  55. Remove Pressure gauges from 1" self-tapping tees and cap tees
  56. Remove vent stack from 1" self-tapping tees and cap tee
  57. Soap Test all fittings
  58. Work Completed — Contact Supervisor and End Session

For a more detailed walkthrough of the module, see the Gas Pipeline Handling User Guide.